Beginning April 8, 2024 – October 31, 2024 Work Details
Road Closures/Lane Restrictions
ROADSIDE WORK ADVISORY: GUARDRAIL SPRAYING
Beginning April 8, 2024 – October 31, 2024 Work Details
Reed Road between Six Mile Creek Road and Allan Road
Duration: August 26 to October 7, 2024 The Reed Road Bridge will be closed due to bridge rehabilitation. Detour: Allan to Vernon to Six Mile Creek
Durand Road between Lansing Road and Bennington Road
Duration: August 21 to October 7, 2024 The Durand Road Bridge will be closed due to bridge rehabilitation. Detour: Bennington to M-71 to Lansing
Meadow Brook Drive between M52 and Riverview Drive
Thursday, September 19, 2024, 8AM to 3PM Road closure due to ditching on M52.
New Lothrop Road bridge between Bath Road and Lehring Road
Closed indefinitely beginning Wednesday, August 2, 2023. (bridge deterioration) Detour Route: Bath Road to Byron Road to Miller Road to Durand Road.